Massive 3D printed schools project in Qatar nears completion

The contractor has completed 14 of 15 planned relocations of its two BODXL 3D printers, with 19,500 square meters of built area finished ahead of a final print expected next week.

Stay up to date with everything that is happening in the wonderful world of AM via our LinkedIn community.

UCC Holding, the Qatar-based construction and infrastructure group building a cluster of 3D printed schools for the country’s Public Works Authority, Ashghal, has completed 19,500 square meters of 3D printed built area and more than 28,000 square meters of printed concrete walls, covering both internal partitions and the external envelope. One printer relocation remains before the project reaches its final print run, expected next week.

UCC Holding leverages 3D printing technology for innovative school constructions in Qatar. Discover their latest progress and plans.The work uses two custom BODXL printers supplied by Denmark’s COBOD International under a contract signed in September 2024. Each unit measures 50 meters long, 30 meters wide and 15 meters tall, making it among the largest construction 3D printers built to date. UCC Holding installed the machines at the Doha site in mid-2025 after running more than 100 full-scale test prints on a smaller BOD2 printer to develop concrete mix designs and validate performance under local conditions.

Moving the printers across the site has required more than repositioning the machines. Each of the 14 completed relocations involved dismantling and moving both BODXL units, relocating the Material Delivery System that feeds them, reinstalling electrical systems and connections, and re-establishing the batching operation, cement silo and raw material logistics at the new location. Crews also had to rebuild the cleaning and pumping areas and recalibrate and test the equipment before printing could resume.

UCC Holding frames the sequence as comprising 15 separate builds of its printing setup since the machines, material-handling system and supporting infrastructure were fully dismantled, transported and recommissioned each time the construction sequence moved to a new section of the site.

UCC Holding leverages 3D printing technology for innovative school constructions in Qatar. Discover their latest progress and plans.

In May 2025, the team completed intensive training alongside COBOD engineers, covering printer operation, print sequencing, structural layering strategies, and live quality control. This milestone marked a major leap in Qatar’s local capacity for advanced construction technology, solidifying its role as a regional hub for innovation and engineering.

Compared to conventional construction methods, 3D printing offers multiple environmental, social, and economic advantages. It significantly reduces raw material waste and minimizes concrete usage, cutting carbon emissions. On-site printing also reduces transport needs, mitigates supply chain risks, and accelerates project delivery. With operations scheduled at night to avoid high temperatures, the process also ensures better concrete performance while reducing dust and noise.

Architecturally, the schools draw inspiration from Qatar’s natural desert formations, with curved, flowing walls resembling sand dunes. This design is only possible because 3D printing offers geometric freedom, enabling organic, parametric forms that would be difficult or too expensive to achieve with traditional construction methods.

The completed work represents the largest 3D printed building unit and the largest 3D concrete printing operation carried out to date, and the company plans to pursue Guinness World Records certification once the final print is complete.